Sl. No.
|
Name of project
|
Approved Cost
(Rs. Cr.)
|
Agency
|
Time Line
|
Project Completion Date
|
Funding Source
|
Amount in BUIDCo (Rs. Cr.)
|
Expense
(Rs. Cr.)
|
Physical Status
(in %)
|
|
1
|
1
|
Buddha Smriti Park
|
130.94
|
Pashwanath Developers
|
9 months
|
31.12.2012
|
State Plan
|
31.91
|
32.02
|
Work in progress
|
|
2
|
Nooranibagh Park, Patna
|
0.80
|
Archana Constructions
|
05 months
|
23.05.2012
|
State Plan
|
0.80
|
0.54
|
Complete
|
|
3
|
Patna Water Supply Project
|
426.98
|
Gammon-Geo Miller
|
24 months
|
28.03.2014
|
JNNURM + State Plan
|
104.46
|
49.69
|
4.65
|
|
4
|
Shaheed Veer Kunwar Singh Azadi Park, Patna
|
2.00
|
Archana Constructions
|
04 months
|
17.05.2013
|
State Plan
|
2.49
|
0.21
|
|
|
2
|
5
|
Khagaul Water Supply Project
|
13.15
|
JP Enterprises
|
12 months
|
28.12.2012
|
JNNURM
|
4.63
|
4.62
|
19.89
|
|
6
|
Danapur Water Supply Project
|
68.96
|
VISHWA-BRCCPL(JV)
|
21 months
|
26.09.2013
|
JNNURM
|
25.86
|
13.53
|
7.87
|
|
7
|
Phulwari Water Supply Project
|
24.70
|
JP-SMS (JV)
|
15 months
|
21.03.2013
|
JNNURM
|
9.26
|
7.01
|
16.37
|
|
8
|
PUA Solid Waste Management
|
11.56
|
Ramky Enviro Engineers Ltd.
|
Continuous
|
Continuous
|
JNNURM
|
4.34
|
3.37
|
Complete
|
|
9
|
Bakhtiyarpur Road with Drainage Project
|
5.11
|
JMD Road Constructions Pvt. Ltd
|
6 months
|
24.01.2012
|
UIDSSMT
|
4.03
|
2.23
|
|
|
10
|
Kankarbagh Park, Patna
|
0.65
|
JMD Road Constructions Pvt. Ltd.
|
12 months
|
19.11.2012
|
State Plan
|
0.65
|
0.65
|
Complete
|
|
11
|
Naubatpur Water Supply
|
9.89
|
|
|
|
State Plan
|
9.89
|
|
Tender Phase
|
|
12
|
Murliganj Road with Drainage Project
|
11.44
|
M/SBaba Hans Constructions pvt. Ltd.
|
9 months
|
01.03.2012
|
UIDSSMT
|
10.96
|
3.86
|
|
|
3
|
13
|
Hajipur Sewerage Project
|
113.62
|
Tri-Tech Infrastructure
|
24 months
|
14.12.2013
|
NGRBA
|
20.87
|
17.68
|
Nil
|
|
14
|
Park Shastrinagar Patna
|
0.85
|
JMD Road Constructions Pvt. Ltd
|
9 months
|
20.07.2012
|
State Plan
|
0.85
|
0.78
|
Complete
|
|
15
|
Rajgir Drainage Project
|
77.67
|
M/s APR project Pvt. ltd. & Ramky Infrastructure Ltd. (IV)
|
12 months
|
15.12.2012
|
State Plan
|
33.10
|
26.04
|
27.30
|
|
16
|
Rajgir Sewerage Project
|
Krushi Infrastructure Pvt. Ltd.
|
9 months
|
15.12.2012
|
State Plan
|
15.37
|
|
4
|
17
|
Bodhgaya Water Supply Project
|
33.56
|
SMC – JITF ( JV)
|
15 months
|
28.03.2013
|
JNNURM
|
10.07
|
8.15
|
16.07
|
|
18
|
Bodhgaya Sewerage Project
|
95.94
|
Ramky Infrastructure Ltd.
|
24 months
|
26.12.2013
|
JNNURM
|
28.79
|
28.35
|
13.73
|
|
5
|
19
|
Begusarai Sewerage Project
|
65.40
|
Tri-Tech Infrastructure
|
24 months
|
14.12.2013
|
NGRBA
|
8.64
|
9.05
|
Nil
|
|
20
|
Munger Sewerage Project
|
187.89
|
IVRCL - HDO - KMB
|
24 months
|
01.04.2014
|
NGRBA
|
35.41
|
12.55
|
Nil
|
|
6
|
21
|
Jhanjharpur Water Supply
|
4.94
|
|
|
|
State Plan
|
1.60
|
|
Tender Phase
|
|
22
|
Muzaffarpur Water Supply Project
|
98.72
|
IVRCL
|
24 months
|
26.12.2013
|
UIDSSMT
|
49.36
|
11.29
|
7.45
|
|
7
|
23
|
Ara Solid Waste Management Project
|
9.84
|
Ramky Infrastructure Ltd.
|
Continuous
|
Continuous
|
UIDSSMT
|
9.80
|
2.09
|
Complete
|
|
24
|
Buxar Sewerage Project
|
74.95
|
Tri-Tech Infrastructure
|
24 months
|
14.12.2013
|
NGRBA
|
6.63
|
5.64
|
1.02
|
|
8
|
25
|
Narkatiyaganj Road with Drainage Project
|
47.13
|
M/S Baibhav Construction pvt. Ltd.
|
9 months
|
23.12.2012
|
UIDSSMT
|
22.71
|
13.96
|
29.10
|
|
26
|
Rosera Road with Drainage Project
|
29.21
|
M/S Baibhav Construction pvt. Ltd.
|
9 months
|
15.12.2012
|
UIDSSMT
|
14.07
|
11.06
|
46.50
|