Bhagalpur Water Supply Project - Phase 1(BWSP-1) under Tranche 1
supported by ADB Loan:
Previous Contract has been terminated on 09.07.2019 due to
non-performance of the Contractor.
New Packages for Balance work of BWSP-1:
•
Balance work bifurcated in 4 packages
for fresh bidding.
•
Notice for invitation of bid issued vide no NCB/11
on 13th April’2020.
•
Two bids received in every package.
•
Technical Bids opened on 03rd June’2020
and Financial Bid on 8th July’2020
•
Name of the bidders under 04 Packages are mentioned below:
SN
|
Package
|
Name of the bidders
|
1
|
Package 01 - BH/WS/01
|
1. KCPL-VRS JV
2. Ganadhipati
Construction Pvt Ltd
|
2
|
Package 02 - BH/WS/01
|
1. NalandaEngicon
Pvt Ltd
2.
KCPL-VRS JV
|
3
|
Package 03 - BH/WS/01
|
1. NalandaEngicon
Pvt Ltd
2.
KCPL-VRS JV
|
4
|
Package 04 - BH/WS/01
|
1. NalandaEngicon
Pvt Ltd
2.
KCPL-VRS JV
|
•
Name of the bidders rejected due to technically non-responsive and
incomplete bid under 04 Packages are mentioned below:
SN
|
Package
|
Name of the bidders
|
1
|
Package 01 - BH/WS/01
|
Ganadhipati Construction Pvt Ltd
|
2
|
Package 02 - BH/WS/01
|
NalandaEngicon Pvt Ltd
|
3
|
Package 03 - BH/WS/01
|
NalandaEngicon Pvt Ltd
|
4
|
Package 04 - BH/WS/01
|
NalandaEngicon Pvt Ltd
|
•
Bidder Quoted, Evaluated Bid Price and Agreement Cost after
Negotiation of the technically responsive bidder under 04 Packages are mentioned
below:
SN
|
Packages
|
Name of the bidder
|
Quoted Price
(INR)
|
Evaluated Price
(INR)
|
Agreement Cost (INR)
|
1
|
Package 01 - BH/WS/01
|
KCPL-VRS JV
|
25,31,46,928.85
|
25,31,46,928.85
|
25,14,93,094.56
|
2
|
Package 02 - BH/WS/01
|
KCPL-VRS JV
|
102,16,87,459.30
|
1,02,16,87,459.30
|
1,01,80,49,230.58
|
3
|
Package 03 - BH/WS/01
|
KCPL-VRS JV
|
101,90,20,488.93
|
1,02,16,48,488.93
|
1,01,54,73,780.25
|
4
|
Package 04 - BH/WS/01
|
KCPL-VRS JV
|
34,04,85,390.32
|
34,04,85,390.32
|